Coordinates are taken at the Abutment Access area on the Ohio side of this dam, near Gallipolis, Ohio. It was put into operation in 1937 with major upgrades in 1992, with two new parallel locks in the West Virginia side.
Waymark Code: WM5PNQ
Location: Ohio, United States
Date Posted: 01/30/2009
Views: 10
Dam
Non-navigable, high-lift, gated dam, top length of gated section 1,132'. Eight roller gates, clear span 125'-6 between 16-foot piers, damming height of 29'- 6' above sills.
Locks
Two new parallel locks, main lock 110' by 1200', auxiliary lock 110' by 600', miter service gates. Locks were activated on January 30, 1993.
Normal upper pool elevation 538.0' m.s.l., upper pool length is 41.7 miles to Racine Dam on Ohio River and 44.6 miles to Winfield Dam on the Kanawha River. Normal upper pool surface area 12,600 acres, normal lower pool elevation 515.0' m.s.l., (upper pool of Greenup Dam), and normal lift 23.0'.
Status
The project was placed in operation 25 August 1937 and completed in October 1937. Lock replacement construction began Nov 1987 and Completed Jan 1993. Rehab of the dam began in Aug 1992 and was finally completed in 2002. 8 new roller gates, control units, motor control center and electric feeders were replaced. In June 2007 the new handicap fishing access and pier was opened to public, the area of fishing is one of the best spots to fish on the Ohio River
==========================
From the U.S. Army Corps of Engineers web site (